For some workcenters, especially paint, more than 1 MO is worked on at a time. If my painter starts several MO's it looks like the total time is out on all of them instead or breaking it out. Am I seeing the correctly and is there a way to have it divide the time up?
Bu soru işaretlendi
In Odoo V18, when multiple Manufacturing Orders (MOs) are worked on at the same workcenter, the system may log the total time equally across all MOs. Odoo does not automatically divide time between MOs.
To resolve this:
Manual Allocation: Adjust time manually for each MO based on work done.
Custom Development: Create a custom module to automatically divide the time.
Workcenter Configuration: Adjust workflows to better track time spent on each MO.
These methods can help accurately allocate time across multiple MOs.
Tartışma hoşunuza mı gidiyor? Sadece okumakla kalmayın, katılın!
Özel özelliklerden yararlanmak ve harika topluluğumuzla etkileşime geçmek için bugün bir hesap oluşturun!
Üye Ol| İlgili Gönderiler | Cevaplar | Görünümler | Aktivite | |
|---|---|---|---|---|
|
|
1
Eyl 24
|
9141 | ||
|
|
0
Tem 16
|
5498 | ||
|
V18 MO allocation question
Çözüldü
|
|
2
Nis 26
|
805 | |
|
|
1
Oca 26
|
1283 | ||
|
|
0
Kas 25
|
1207 |