For some workcenters, especially paint, more than 1 MO is worked on at a time. If my painter starts several MO's it looks like the total time is out on all of them instead or breaking it out. Am I seeing the correctly and is there a way to have it divide the time up?
Этот вопрос был отмечен
In Odoo V18, when multiple Manufacturing Orders (MOs) are worked on at the same workcenter, the system may log the total time equally across all MOs. Odoo does not automatically divide time between MOs.
To resolve this:
Manual Allocation: Adjust time manually for each MO based on work done.
Custom Development: Create a custom module to automatically divide the time.
Workcenter Configuration: Adjust workflows to better track time spent on each MO.
These methods can help accurately allocate time across multiple MOs.
Не оставайтесь в стороне – присоединяйтесь к обсуждению!
Создайте аккаунт сегодня, чтобы получить доступ к эксклюзивным функциям и стать частью нашего замечательного сообщества!
Регистрация| Похожие посты | Ответы | Просмотры | Активность | |
|---|---|---|---|---|
|
|
1
сент. 24
|
9148 | ||
|
|
0
июл. 16
|
5499 | ||
|
V18 MO allocation question
Решено
|
|
2
апр. 26
|
810 | |
|
|
1
янв. 26
|
1283 | ||
|
|
0
нояб. 25
|
1207 |