I have MO-01 for Product #1, and MO-02 for product #2 (both with different BoM). Final products operation is to bake it in owen. Owen WC(Work center) capacity is 2.
How could i "bake" two MO at the same time? Becouse I cant do 'Bake' operation at the same time. Clock is ticking only for one MO.