Can I also plan projects that don't have orders? For example, internal projects? Can I also plan on specific tasks within the project?
Esta pregunta ha sido marcada
Hope it helps.
How to do it:
Go to Project → Create and create a new project.
Make sure “Billable” or Sales Order linkage is disabled (or simply don’t create it from a quotation).
Enable Planning / Tasks / Timesheets as needed from the project settings.
Create tasks manually and assign:
Start and end dates
Employees
Planned hours
Use the Planning app (if installed) to schedule resources directly on tasks.
Key point:
Sales orders are not mandatory for project planning. They are only required if you want billing, invoicing, or sales-driven project creation.
This approach works well for:
Internal projects
R&D or maintenance work
IT / HR / Admin projects
Non-billable or fixed-budget initiatives
¿Le interesa esta conversación? ¡Participe en ella!
Cree una cuenta para poder utilizar funciones exclusivas e interactuar con la comunidad.
Inscribirse| Publicaciones relacionadas | Respuestas | Vistas | Actividad | |
|---|---|---|---|---|
|
|
0
oct 25
|
4551 | ||
|
|
0
mar 26
|
8 | ||
|
|
1
may 25
|
7179 |