In the manufacturing app, "Planning by Production" view, I can reschedule work orders by dragging them to different timeslots.
I'd like to do this at the MO level so that the entire MO can be shifted to a different timeslot. Is this possible?
In the manufacturing app, "Planning by Production" view, I can reschedule work orders by dragging them to different timeslots.
I'd like to do this at the MO level so that the entire MO can be shifted to a different timeslot. Is this possible?
In effect what you trying to achieve is to change the 'scheduled date' of a MO. You can drag and drop to change it while on the calendar view of Operations > Manufacturing Orders menu
By doing so it does change the MO to an unplanned state.
Crie uma conta hoje mesmo para aproveitar os recursos exclusivos e interagir com nossa incrível comunidade!
Inscrever-se| Publicações relacionadas | Respostas | Visualizações | Atividade | |
|---|---|---|---|---|
|
1
fev. 26
|
4165 | |||
|
2
fev. 26
|
3694 | |||
|
Sub Manufacturing orders planning
Resolvido
|
2
jun. 23
|
4643 | ||
|
2
ago. 22
|
7199 | |||
|
1
mar. 22
|
4193 |
1. Use the live chat to ask your questions.
2. The operator answers within a few minutes.