In the manufacturing app, "Planning by Production" view, I can reschedule work orders by dragging them to different timeslots.
I'd like to do this at the MO level so that the entire MO can be shifted to a different timeslot. Is this possible?
In the manufacturing app, "Planning by Production" view, I can reschedule work orders by dragging them to different timeslots.
I'd like to do this at the MO level so that the entire MO can be shifted to a different timeslot. Is this possible?
In effect what you trying to achieve is to change the 'scheduled date' of a MO. You can drag and drop to change it while on the calendar view of Operations > Manufacturing Orders menu
By doing so it does change the MO to an unplanned state.
Crea un account oggi per scoprire funzionalità esclusive ed entrare a far parte della nostra fantastica community!
Registrati| Post correlati | Risposte | Visualizzazioni | Attività | |
|---|---|---|---|---|
|
1
feb 26
|
4255 | |||
|
2
feb 26
|
3915 | |||
|
2
giu 23
|
4720 | |||
|
2
ago 22
|
7322 | |||
|
1
mar 22
|
4304 |
1. Use the live chat to ask your questions.
2. The operator answers within a few minutes.