How can I automatically set a deadline in two weeks when I create a new task in a specific project?
This question has been flagged
1
Atsakyti
6189
Rodiniai
Create an automated action with a "In New Stage" filter as post condition. Trigger an server action type write and set the following formula for the deadline:
time.strftime('%Y-%m-%d %H:%M:%S',time.gmtime(time.time()+14*24*3600))