In Project tasks kanban view there is a button "+" (for each stage) to "quick create" a task for a stage. How to make this button open not "a quick create" (small form) but instead open a "Task create" form for that stage? So that when the user clicks "+" on the stage then the user is redirected to the "New task" form (and the stage is preselected). Much like when the user clicks "New" button to create a task.
신고된 질문입니다
1
회신
6065
화면
One can use module "Optional quick create" to achieve that functionality.