Hello I have a question regarding consumption of partialities of products for a BOM.
For example if i'm manufacturing a table, but I only need half of a piece of wood for it, how should I list it in the BOM?
Thanks in advance for your help
Hello I have a question regarding consumption of partialities of products for a BOM.
For example if i'm manufacturing a table, but I only need half of a piece of wood for it, how should I list it in the BOM?
Thanks in advance for your help
You can easily consume 0.4m, or 0.5 units, depending on how your unit of measure is configured. Check that the rounding of your unit of measure is 0.1 or 0.01.