Currently
in Odoo, we can setup 2 step picking for receipts, delivery, and manufacturing,
but not for the subcontracting route.
Pertanyaan ini telah diberikan tanda
1. Activate the
subcontracting route on the Manufacturing module.
2. Go to the Inventory module > Configuration > Operation Type
3. Create a new operation, with the type Internal Transfer, and set the source location to be the picking location, and destination location to be the output location:
4. Go to the Inventory module >
Configuration > Routes > Resupply Subcontractor
5. Change the current rule to the
following configuration:
6. Create a new rule with the following
configuration:
Make sure to set the two rules on the following order:
Now, when the user creates the PO for the trigger the
subcontracting process, there will be a picking operation before the delivery:
Menikmati diskusi? Jangan hanya membaca, ikuti!
Buat akun sekarang untuk menikmati fitur eksklufi dan agar terlibat dengan komunitas kami!
Daftar| Post Terkait | Replies | Tampilan | Aktivitas | |
|---|---|---|---|---|
|
|
1
Jun 21
|
5198 | ||
|
|
3
Mar 25
|
24321 | ||
|
|
2
Mei 21
|
13154 | ||
|
|
1
Feb 22
|
5433 | ||
|
|
2
Okt 25
|
7310 |