Currently
in Odoo, we can setup 2 step picking for receipts, delivery, and manufacturing,
but not for the subcontracting route.
Cette question a été signalée
1. Activate the
subcontracting route on the Manufacturing module.
2. Go to the Inventory module > Configuration > Operation Type
3. Create a new operation, with the type Internal Transfer, and set the source location to be the picking location, and destination location to be the output location:
4. Go to the Inventory module >
Configuration > Routes > Resupply Subcontractor
5. Change the current rule to the
following configuration:
6. Create a new rule with the following
configuration:
Make sure to set the two rules on the following order:
Now, when the user creates the PO for the trigger the
subcontracting process, there will be a picking operation before the delivery:
Vous appréciez la discussion ? Ne vous contentez pas de lire, rejoignez-nous !
Créez un compte dès aujourd'hui pour profiter de fonctionnalités exclusives et échanger avec notre formidable communauté !
S'inscrire| Publications associées | Réponses | Vues | Activité | |
|---|---|---|---|---|
|
|
1
juin 21
|
5199 | ||
|
|
3
mars 25
|
24322 | ||
|
|
2
mai 21
|
13156 | ||
|
|
1
févr. 22
|
5433 | ||
|
|
2
oct. 25
|
7311 |