I would like to run the mrp procurement planner manually v7
Pertanyaan ini telah diberikan tanda
2
Replies
6596
Tampilan
Go to menu "Warehouse / Scheduler / Run Schedulers"
Note: Make sure you have the option "technical features" activated for your user in Settings > Users.
For V7 ???
Yes, this is for v7.
found it. thanks a lot!!
Is this applicable to MRP scheduler as well? I have tried it but no affect.