How can i display Gantt info in the project task ( project module) , add start date and end date for tasks
Dette spørgsmål er blevet anmeldt
1
Svar
6023
Visninger
In Project v13 the View Gantt was available and by activating the developer mode, inside Task > Extra Info it was possible to add a "Start date" and "End date".
Unfortunately, in v14, the Gantt functionality is no longer available in the Project App and requires the Planning App, which has undergone major improvements, including integration with the Project app!
BR
Ricardo
Kan du lide at diskutere? Læs ikke bare med, deltag aktivt i debatten!
Opret en konto i dag for at få glæde af eksklusive funktioner, og bliv en del af vores skønne fællesskab!
Tilmeld dig| Relaterede indlæg | Besvarelser | Visninger | Aktivitet | |
|---|---|---|---|---|
|
|
1
feb. 26
|
1763 | ||
|
|
1
dec. 25
|
2233 | ||
|
|
1
okt. 25
|
3782 | ||
|
|
1
jun. 23
|
5701 | ||
|
|
1
nov. 22
|
6010 |
To increase the interest in your question improving the response potential, it would be good to better elaborate the question, for example: How can I access Gantt view in project v14?
Actually,i m in entreprise version, free trial