How can I automatically set a deadline in two weeks when I create a new task in a specific project?
This question has been flagged
1
Respondre
6165
Vistes
Create an automated action with a "In New Stage" filter as post condition. Trigger an server action type write and set the following formula for the deadline:
time.strftime('%Y-%m-%d %H:%M:%S',time.gmtime(time.time()+14*24*3600))
Enjoying the discussion? Don't just read, join in!
Create an account today to enjoy exclusive features and engage with our awesome community!
Registrar-se| Related Posts | Respostes | Vistes | Activitat | |
|---|---|---|---|---|
|
|
0
de des. 24
|
7459 | ||
|
|
3
d’abr. 24
|
4209 | ||
|
|
1
de set. 23
|
3901 | ||
|
|
5
de jul. 20
|
7887 | ||
|
|
0
de març 17
|
4920 |