when creating task forecast start date 1-1-2017 end date 1-2-2017 which mean it will take two days and % time showing 50% as the employee working 9 hours a day but Gantt forecast by resource highlight one one day ?! any when can explain to me ?!
This question has been flagged
4526
Vistes
Enjoying the discussion? Don't just read, join in!
Create an account today to enjoy exclusive features and engage with our awesome community!
Registrar-se| Related Posts | Respostes | Vistes | Activitat | |
|---|---|---|---|---|
|
|
0
de jul. 22
|
3223 | ||
|
|
1
de febr. 26
|
1563 | ||
|
|
1
de des. 25
|
2045 | ||
|
|
1
de des. 23
|
5417 | ||
|
|
1
de juny 23
|
5548 |