In the manufacturing app, "Planning by Production" view, I can reschedule work orders by dragging them to different timeslots.
I'd like to do this at the MO level so that the entire MO can be shifted to a different timeslot. Is this possible?
In the manufacturing app, "Planning by Production" view, I can reschedule work orders by dragging them to different timeslots.
I'd like to do this at the MO level so that the entire MO can be shifted to a different timeslot. Is this possible?
In effect what you trying to achieve is to change the 'scheduled date' of a MO. You can drag and drop to change it while on the calendar view of Operations > Manufacturing Orders menu
By doing so it does change the MO to an unplanned state.
أنشئ حساباً اليوم لتستمتع بالخصائص الحصرية، وتفاعل مع مجتمعنا الرائع!
تسجيل| المنشورات ذات الصلة | الردود | أدوات العرض | النشاط | |
|---|---|---|---|---|
|
1
فبراير 26
|
4164 | |||
|
2
فبراير 26
|
3690 | |||
|
2
يونيو 23
|
4642 | |||
|
2
أغسطس 22
|
7198 | |||
|
1
مارس 22
|
4193 |
1. Use the live chat to ask your questions.
2. The operator answers within a few minutes.