I have tried several ways of exporting & importing (inc. the external id) to update the component level in the bill of materials but always get duplicate lines of components. I cannot figure out how I can do this & end up with the original component line but with an amended quantity. Anyone?
Această întrebare a fost marcată
Please select BOM Lines/External ID
Hi,
you must export not only the BOM external id but also components lines external ids. did you do it and still get the same described result ?
Hello,
You also need to export the BoM Line external id. If you forgot to export line external id then it duplicate the lines.
You have to export two external id.
1) BoM external id
2) BoM Lines external id
Thanks everyone. I have now managed to get the correct results thanks to your responses :)
Îți place discuția? Nu doar citi, alătură-te!
Creează-ți un cont astăzi pentru a beneficia de funcții exclusive și a interacționa cu minunata noastră comunitate!
Înscrie-te| Postări similare | Răspunsuri | Vizualizări | Activitate | |
|---|---|---|---|---|
|
|
1
mar. 26
|
1051 | ||
|
|
3
feb. 25
|
2636 | ||
|
|
0
oct. 25
|
2852 | ||
|
|
1
iun. 25
|
6659 | ||
|
|
0
feb. 19
|
5705 |