Hi,
I'm using Odoo 18, and I want to calculate the costs and time based on employees available on a work center.
For example, a work center capacity is 10 employees, but 2 of them are absent today so the capacity today is 8 employees, how should I manage that, so Odoo calculates the correct time and costs today.
I only see the capacity as total of employees, or should I change the capacity of a work center each day? Is it a good practice?
Cette question a été signalée
3
Réponses
5129
Vues
the current option available in Odoo is that it will calculate the cost and time based on actual execution of MO by using the resources (employee assigned to workcenter) you have, but your question is about calculating based on configuration / employee attendance, which can only be done with customization
I was wondering the same, maybe we reach the same conclusion, that we can't?
Regards.
Vous appréciez la discussion ? Ne vous contentez pas de lire, rejoignez-nous !
Créez un compte dès aujourd'hui pour profiter de fonctionnalités exclusives et échanger avec notre formidable communauté !
S'inscrire| Publications associées | Réponses | Vues | Activité | |
|---|---|---|---|---|
|
|
1
juin 26
|
1047 | ||
|
|
1
juil. 25
|
5536 | ||
|
For manfacturing order
Résolu
|
|
1
juil. 25
|
4276 | |
|
|
1
mars 25
|
5198 | ||
|
|
3
déc. 25
|
9648 |