Hello,
How can I automate the status update of a parent task?
I would like the parent task to be updated to "done" when all its blocking subtasks are done.
Is it possible?
Thank you for your help!
Hello,
How can I automate the status update of a parent task?
I would like the parent task to be updated to "done" when all its blocking subtasks are done.
Is it possible?
Thank you for your help!
You could try this:
Settings > Techincal > Automated Actions:
Model: Task
Trigger: On Update
Trigger Fields: Blocked By
Before Update Domain: Blocked By > Stage > Name = "in progress"
Domain: Blocked By > Stage > Name = "done"
Action To Do: Update the Record
Data to Write:
Field: Stage (project.task)
Evaluation Type: Reference
Record: Done
Create an account today to enjoy exclusive features and engage with our awesome community!
Sign up| Related Posts | Replies | Views | Activity | |
|---|---|---|---|---|
|
2
May 25
|
2740 | |||
|
1
Apr 20
|
4000 | |||
|
2
Sep 23
|
5329 | |||
|
2
May 17
|
10389 | |||
|
1
Feb 26
|
1587 |
1. Use the live chat to ask your questions.
2. The operator answers within a few minutes.