We have set up recurring project tasks and saw the note in the Recurrence tab of tasks as to when the next occurences are. But what is next? We have run the cron "Project: Create Recurring Tasks" but it is not clear to us what is the expected output of this scheduled action.
Dette spørgsmål er blevet anmeldt
1
Svar
3218
Visninger
Hi @Top C, C Biteng,
Actually effect will run from the next day, because cron method check the today date with recurrence occurrence date which we mention on task. Normally its started from next day. So on next day automatic new task is created.
for more reference https://www.youtube.com/watch?v=Pet5qVSh8xQ
Thanks! Video was helpful
Kan du lide at diskutere? Læs ikke bare med, deltag aktivt i debatten!
Opret en konto i dag for at få glæde af eksklusive funktioner, og bliv en del af vores skønne fællesskab!
Tilmeld dig| Relaterede indlæg | Besvarelser | Visninger | Aktivitet | |
|---|---|---|---|---|
|
|
1
jan. 24
|
3138 | ||
|
|
0
feb. 24
|
3902 | ||
|
|
2
okt. 23
|
4046 | ||
|
|
3
sep. 23
|
4537 | ||
|
Project and Tasks
Løst
|
|
1
jul. 23
|
4163 |